RCKC Construction Update for the Week of 7-29-24

(posted Jul 25, 2024)

FOR IMMEDIATE RELEASE
DATE: FRIDAY, JULY 26, 2024

Sign up for RCKC CONNECT to receive message alerts for road construction, road closures/detours, and general public news from the Road Commission of Kalamazoo County website at: www.kalamazoocountyroads.com

Kalamazoo, MI-            

In an effort to keep local drivers informed of the latest traffic and road maintenance operations by the Road Commission, we have provided the following update for the week of July 29, 2024.  For further information call 269-381-3171 or visit RCKC website www.kalamazoocountyroads.com.

“This information is made available to assist motorists in planning for construction delays,” Joanna Johnson, Managing Director of the Road Commission said. “Motorists are reminded to be alert, slow down, stay informed, and be cautious when approaching a work zone. Remember, these projects signify progress in improving our infrastructure!”

Please note: This information is subject to change. Projects, road closures and timing can change from day to day, depending upon a number of factors, and traffic delays can develop in a matter of minutes due to weather conditions, emergency situations, etc.

 

Alamo Township

Road: AB Avenue - 1st Street to 7,900' east of 1st Street
Current Status: Tree removal and chip seal to follow.
Detour: None
Project Information: This project includes pulverize, double chip seal
Start Date: June 25, 2024
End Date: August 31, 2024

 

Road: D Avenue - 6th Street to Ravine Road
Current Status: Tree removal and trimming complete. Road work to begin 8/12.
Detour: None
Project Information: This project includes tree removal and trimming, drainage improvements, asphalt paving, and restoration. 
Start Date: April 8, 2024
End Date: September 30, 2024

******************************************************************

Charleston Township

Road: Mercury Drive - MN Avenue to East Michigan Avenue
Current Status: Tree trimming and centerline fog seal week of 7/29.. MN Avenue will be closed from 44th Street to Mercury Drive.
Detour: MN Avenue and Mercury Drive will be closed to through traffic during the project. The detour route is East Michigan Avenue and 40th Street.
Project Information: This project includes asphalt milling and resurfacing and some curb and gutter installation.
Start Date: May 28, 2024
End Date: August 2, 2024

 

Road: MN Avenue - 44th Street to Mercury Drive
Current Status: Tree trimming and centerline fog seal week of 7/29. At this time, MN Avenue will be closed from 44th Street to Mercury Drive.
Detour: MN Avenue and Mercury Drive will be closed to through traffic during the project. The detour route is East Michigan Avenue and 40th Street.
Project Information: This project includes widening for a turn lane at 44th Street, milling and paving, and realignment of the intersection of MN Avenue at Mercury Drive.
Start Date: May 28, 2024
End Date: August 2, 2024

******************************************************************

Comstock Township

Road: ML Avenue - Sprinkle Road to 26th Street
Current Status: Restoration and shoulder gravel forthcoming. 
Detour: None
Project Information: This project includes asphalt milling, asphalt paving, drainage
improvements, curb & gutter replacement, and restoration.

Start Date: May 28, 2024
End Date: August 7, 2024

******************************************************************

Kalamazoo Township

Road: Davis-Omstead Drain - Olmstead Road to Olmstead Road
Current Status: Culvert installaton continuing week of 7/29. 
Detour: Brookfield Avenue and Springfield Avenue will be closed at alternate times during the project. The detour route is around the block on either Greenfield Avenue or Market Street.
Project Information: This project includes culvert replacement at two road crossings in addition to stream bank restoration.
Start Date: April 1, 2024
End Date: October 25, 2024

 

Road: Squires Drive - Drake Road to Ravine Road
Current Status: Restoration, signing, and pavement markings the week of 7/29.  The intersection will be closed and a detour route will be posted. 

Emergency response teams are aware of the closures. 

Detour: Squires Drive/H Avenue will be closed. The detour route is 10th Street, West Main, Nichols and Ravine Road. Drake Road will be closed to through traffic. The detour is Grand Prairie, Nichols, and Ravine Road. 
Project Information: This project includes construction of a roundabout at the intersection of Drake Road at Squires Drive. Squires Drive will also be reconstructed with shoulder widening and drainage improvements.
Start Date: March 1, 2024
End Date: August 9, 2024

 

Road:  Douglas Avenue - City of Kalamazoo Limits to Barney Road/Mosel Avenue
Current Status: Paving is anticipated week of 7/29. The road will be closed between Mosel Ave and US131 BL.
Project Information: This project includes milling and resurfacing, storm sewer improvements, and curb and gutter replacement.
Start Date: April 26, 2024
End Date: August 30, 2024

******************************************************************

Oshtemo Township

Road: 9th Street - Stadium Drive to KL Avenue
Current Status: Roadside restoration the week of 7/29.
Detour: None
Project Information: This project includes asphalt milling, asphalt paving, manhole adjustments, tree trimming, and restoratiion. 
Start Date: April 15, 2024
End Date: August 10, 2024

 

Road: Stadium Drive - 8th Street to 9th Street
Current Status: Adjusting manholes, roadside restoration, pavment markings for the week of 7/29.
Project Information: This project includes asphalt milling, asphalt paving, manhole adjustments, tree trimming, and restoration.
Start Date: April 15, 2024
End Date: August 10, 2024

******************************************************************

Pavilion Township

Road: T Avenue - 34th Street to 36th Street
Current Status: Awaiting pavement markings. 
Detour: None
Project Information: Rubber Chip Seal
Start Date: June 21, 2024
End Date: August 31, 2024

******************************************************************

Prairie Ronde Township

Road: 6th Street - XY Avenue to W Avenue, WX Avenue - 6th Street to 6th Street
Current Status: Awaiting Fog Seal
Detour: None
Project Information: Rubber Chip Seal and Fog Seal
Start Date: June 24, 2024
End Date: August 14, 2024

 

Road: YZ Avenue - 7th Street to 125' east of Prairie Brook Street
Current Status: Awaiting Fog Seal
Detour: None
Project Information: Rubber Chip Seal and Fog Seal
Start Date: June 24, 2024
End Date: August 14, 2024

******************************************************************

Richland Township

Road: Greer Drive - 35th Street to 4,600' east of 35th Street
Current Status: Tree work complete, drainage improvements to follow.
Detour: None
Project Information: HMA Overlay
Start Date: May 13, 2024
End Date: August 14, 2024

******************************************************************

Texas Township

Road: 1st Street - P Avenue to 2,587' north of P Avenue
Current Status: Shoulder gravel, restoration to follow.
Detour: None
Project Information: HMA Overlay, drainage improvement and tree work
Start Date: April 26, 2024
End Date: August 30, 2024

 

Road: 2nd Street - R Avenue to Q Avenue
Current Status: Driveway adjustments, stump grinding, drainage improvments are forthcoming. 
Detour: None
Project Information: Tree pruning and removal, HMA paving, shoulder gravel, restoration.
Start Date: July 15, 2024
End Date: September 30, 2024

 

Road: 1st Street - 3,306' south of Stadium Drive to Stadium Drive
Current Status: Shoulder gravel, restoration to follow.
Detour: None
Project Information: Tree pruning and removal, HMA cold milling and paving, shoulder gravel, ditch cleanout, restoration.
Start Date: July 15, 2024
End Date: September 30, 2024

 

Road: PQ Avenue - 3rd Street to 4th Street
Current Status: Driveway adjustments, stump grinding,drainage improvments are forthcoming. 
Detour: None
Project Information: Tree pruning and removal, HMA cold milling and paving, shoulder gravel, ditch cleanout, restoration.
Start Date: May 28, 2024
End Date: August 14, 2024

******************************************************************

Wakeshma Township

Road: W Avenue - 42nd Street to 44th Street
Current Status: Week of 7/29 restoration and pavement markings are anticipated to occur. Road will remain closed.
Detour: W Avenue will be closed and detoured to traffic. The detour route is 42nd Street, R Avenue, 1/2 Mile Road, K Drive S, 2 Mile Road, O Drive S, and 1 1/2 Mile Road. 
Project Information: This project includes roadway crushing, shaping, resurfacing, shoulder widening, and drainage improvements. 
Start Date: April 1, 2024
End Date: August 2, 2024

******************************************************************

County Wide Projects

Road: Pavement Marking on various roads in Kalamazoo County
Current Status: Pavement markings installation on projects countywide. 
Detour: Expect delays in work zones. Please do not follow pavement marking operations too close, as to avoid potential paint on vehicles. 
Project Information: Pavement marking on various roads in Kalamazoo County. 
Start Date: June 3, 2024
End Date: November 15, 2024

###

For file attachment (PDF), click here