(posted Apr 16, 2026)
FOR IMMEDIATE RELEASE
DATE: Thursday, April 16, 2026
Sign up for RCKC CONNECT to receive message alerts for road construction, road closures/detours, and general public news from the Road Commission of Kalamazoo County website at: www.kalamazoocountyroads.com
Kalamazoo, MI-
In an effort to keep local drivers informed of the latest traffic and road maintenance operations by the Road Commission, we have provided the following update. For further information call 269-381-3171 or visit RCKC website www.kalamazoocountyroads.com.
“This information is made available to assist motorists in planning for construction delays,” Travis Bartholomew, Managing Director of the Road Commission said. “Motorists are reminded to be alert, slow down, stay informed, and be cautious when approaching a work zone. Remember, these projects signify progress in improving our infrastructure!”
Please note: This information is subject to change. Projects, road closures and timing can change from day to day, depending upon a number of factors, and traffic delays can develop in a matter of minutes due to weather conditions, emergency situations, etc.
******************************************************************
Comstock Township
Road: Midlink Drive - Park Circle Drive to Old Cork Street
Current Status: Manhole adjustments, milling, and paving will begin the week of 4/20.
Detour: None
Project Information: Manhole adjustments, milling, and hot mix asphalt (HMA) resurfacing.
Start Date: April 15, 2026
End Date: October 15, 2026
Road: Midlink Drive - Sprinkle Road to Midlink Drive
Current Status: Manhole adjustments, milling, and paving will begin the week of 4/20.
Detour: None
Project Information: Manhole adjustments, milling, and HMA resurfacing.
Start Date: April 15, 2026
End Date: October 15, 2026
******************************************************************
Oshtemo Township
Road: 9th Street - Stadium Drive to Quail Run
Current Status: Excavation and sidewalk grading week of 4/20.
Detour: Traffic control shall consist of a shoulder and lane closure with a lane shift on a 3-lane undivided roadway.
Project Information: Constructing a sidewalk along 9th Street. Project includes curbs, ramps, and drainage improvements.
Start Date: March 30, 2026
End Date: June 26, 2026
******************************************************************
Texas Township
Road: 5th Street - N Eagle Lake Drive to OP Avenue
Current Status: Tree removals are complete.
Detour: None
Project Information: Tree clearing, milling, and paving.
Start Date: April 6, 2026
End Date: June 1, 2026
Road: E Eagle Lake Drive - 950' south of OP Avenue to OP Avenue
Current Status: Tree removals are complete.
Detour: None
Project Information: Tree clearing, milling, and paving.
Start Date: April 6, 2026
End Date: June 2, 2026
******************************************************************
Wakeshma Township
Road: X Avenue - 40th Street to 42nd Street
Current Status: Gravel placement and pulverize.
Detour: None
Project Information: Gravel placement and pulverize.
Start Date: April 13, 2026
End Date: November 15, 2026
******************************************************************
Countywide Projects
Road: Hot Mix Asphalt Wedging on various roads in Kalamazoo County.
Current Status: Wedging will continue in various townships.
Detour: None
Project Information: Placing short stretches of asphalt pavement to bridge small areas of excessive cracking or to correct road shape.
Start Date: April 15, 2026
End Date: October 15, 2026
###