RCKC Construction Update for the Week of 7-6-26

(posted Jul 01, 2026)

FOR IMMEDIATE RELEASE
DATE: Thursday, July 1, 2026

Sign up for RCKC CONNECT to receive message alerts for road construction, road closures/detours, and general public news from the Road Commission of Kalamazoo County website at: www.kalamazoocountyroads.com

Kalamazoo, MI-            

In an effort to keep local drivers informed of the latest traffic and road maintenance operations by the Road Commission, we have provided the following update. For further information call 269-381-3171 or visit RCKC website www.kalamazoocountyroads.com.

“This information is made available to assist motorists in planning for construction delays,” Travis Bartholomew, Managing Director of the Road Commission said. “Motorists are reminded to be alert, slow down, stay informed, and be cautious when approaching a work zone. Remember, these projects signify progress in improving our infrastructure!”

Please note: This information is subject to change. Projects, road closures and timing can change from day to day, depending upon a number of factors, and traffic delays can develop in a matter of minutes due to weather conditions, emergency situations, etc.

******************************************************************

Alamo Township

Road: AB Avenue - 7,900' east of 1st Street to Ravine Road
Current Status: Week of 7/6, grading and drainage improvements. 
Detour: None
Project Information: RCKC preventive maintenance.
Start Date: April 15, 2026
End Date: October 15, 2026

******************************************************************

Brady Township

Road: West Indian Lake Drive - 1,500' north of UV Avenue to 2,300' north of UV Avenue
Current Status: Milling and paving forthcoming. 
Detour: None
Project Information: Replacing cross culvert.
Start Date: April 15, 2026
End Date: October 15, 2026

******************************************************************

Charleston Township

Road: 38th Street - 5,000 south of G Avenue to G Avenue
Current Status: Awaiting fog seal construction joint.
Detour: None
Project Information: RCKC Preventive Maintenance.
Start Date: May 14, 2026
End Date: October 15, 2026

******************************************************************

Comstock Township

Road: Beth Ann Avenue - Nichole Street to Ilene Street
Current Status: Awaiting fog seal construction joint.
Detour: None
Project Information: Manhole adjustments, drainage improvements, milling, and hot mix asphalt (HMA) resurfacing.
Start Date: April 15, 2026
End Date: October 15, 2026

 

Road: Shadow Lane Avenue - Sarah Street to Kimberly Street
Current Status: Awaiting fog seal construction joint.
Detour: None
Project Information: Manhole adjustments, drainage improvements, milling, and hot mix asphalt (HMA) resurfacing.
Start Date: April 15, 2026
End Date: October 15, 2026

 

Road: Blake Boulevard - Nichole Street to 35th Street
Current Status: Awaiting fog seal construction joint.
Detour: None
Project Information: Manhole adjustments, drainage improvements, milling, and hot mix asphalt (HMA) resurfacing.
Start Date: April 15, 2026
End Date: October 15, 2026

 

Road: Courtney Street - 433' south of Shadow Lane Avenue to Blake Boulevard
Current Status: Awaiting fog seal construction joint.
Detour: None
Project Information: Manhole adjustments, drainage improvements, milling, and hot mix asphalt (HMA) resurfacing.
Start Date: April 15, 2026
End Date: October 15, 2026

 

Road: Cynthia Street - 433' south of Shadow Lane Avenue to Blake Boulevard
Current Status: Awaiting fog seal construction joint.
Detour: None
Project Information: Manhole adjustments, drainage improvements, milling, and hot mix asphalt (HMA) resurfacing.
Start Date: April 15, 2026
End Date: October 15, 2026

 

Road: Ilene Street - Beth Ann Avenue to Blake Boulevard
Current Status: Awaiting fog seal construction joint.
Detour: None
Project Information: Manhole adjustments, drainage improvements, milling, and hot mix asphalt (HMA) resurfacing.
Start Date: April 15, 2026
End Date: October 15, 2026

 

Road: Miah Street - Sarah Street to Mildred Street
Current Status: Awaiting fog seal construction joint.
Detour: None
Project Information: Manhole adjustments, drainage improvements, milling, and hot mix asphalt (HMA) resurfacing.
Start Date: April 15, 2026
End Date: October 15, 2026

 

Road: Mildred Street - Shadow Lane Avenue to Miah Street
Current Status: Awaiting fog seal construction joint.
Detour: None
Project Information: Manhole adjustments, drainage improvements, milling, and hot mix asphalt (HMA) resurfacing.
Start Date: April 15, 2026
End Date: October 15, 2026

 

Road: Nichole Street - Beth Ann Avenue to Blake Boulevard
Current Status: Awaiting fog seal construction joint.
Detour: None
Project Information: Manhole adjustments, drainage improvements, milling, and hot mix asphalt (HMA) resurfacing.
Start Date: April 15, 2026
End Date: October 15, 2026

 

Road: Sarah Street - 419' south of Shadow Lane Avenue and Miah Street
Current Status: Awaiting fog seal construction joint.
Detour: None
Project Information: Manhole adjustments, drainage improvements, milling, and hot mix asphalt (HMA) resurfacing.
Start Date: April 15, 2026
End Date: October 15, 2026

 

Road: Claxton Street - 1,159' south of East Cork Street to East Cork Street
Current Status: Awaiting fog seal construction joint.
Detour: None
Project Information: Manhole adjustments, drainage improvements, milling, and hot mix asphalt (HMA) resurfacing.
Start Date: April 15, 2026
End Date: October 15, 2026

 

Road: Heath Avenue - 166' west of Senne Street to 166' east of Claxton Street
Current Status: Awaiting fog seal construction joint.
Detour: None
Project Information: Manhole adjustments, drainage improvements, milling, and hot mix asphalt (HMA) resurfacing.
Start Date: April 15, 2026
End Date: October 15, 2026

 

Road: Senne Street - 1,159' south of East Cork Street to East Cork Street
Current Status: Awaiting fog seal construction joint.
Detour: None
Project Information: Manhole adjustments, drainage improvements, milling, and hot mix asphalt (HMA) resurfacing.
Start Date: April 15, 2026
End Date: October 15, 2026

 

Road: Midlink Drive - Park Circle Drive to Old Cork Street
Current Status: Awaiting pavement markings.
Detour: None
Project Information: Manhole adjustments, milling, and hot mix asphalt (HMA) resurfacing.
Start Date: April 15, 2026
End Date: October 15, 2026

 

Road: Midlink Drive - Sprinkle Road to Midlink Drive
Current Status: Awaiting pavement markings.
Detour: None
Project Information: Manhole adjustments, milling, and HMA resurfacing.
Start Date: April 15, 2026
End Date: October 15, 2026

 

Road: Comstock Avenue - Sprinkle Road to River Street
Current Status: Week of 7/6, work will include the removal and installation of storm sewer drainage structures throughout the project area. Existing storm sewer pipes will be cleaned, televised, and lined. Consumers Energy will also be on site wrapping up gas main replacement in coordination with the project. 
Detour: Comstock Avenue will be closed to through traffic and detoured using River Street, I-94 BL, and Sprinkle Road. 
Project Information: 0.85 miles of asphalt milling and resurfacing, concrete curb and gutter replacement, and storm sewer replacement.
Start Date: June 1, 2026
End Date: August 21, 2026

******************************************************************

Kalamazoo Township

Road: Drake Road - Grand Prairie to Squires Drive
Current Status: Milling is anticipated for July 9 and paving for July 11.
Detour: Drake Road will remain open to traffic. Motorists should expect delays when work is ongoing.
Project Information: 0.50 miles of asphalt milling and resurfacing.
Start Date: July 1, 2026
End Date: August 1, 2026

******************************************************************

Oshtemo Township

Road: 9th Street - KL Avenue to West Main Street
Current Status: Lowering manholes, curb/sidewalk removals, and placement the week of 7/6. A traffic shift will need to occur for this work. 
Detour: Lane closures are anticipated. No roadway closure or detour is anticipated. 
Project Information: 1.06 miles of asphalt milling and resurfacing with a sidewalk ramp.
Start Date: June 1, 2026
End Date: August 1, 2026

 

Road: 9th Street - Stadium Drive to Quail Run
Current Status: Restoration and sign installation are planned for the week of 7/6.
Detour: Traffic control shall consist of a shoulder and lane closure with a lane shift on a 3-lane undivided roadway.
Project Information: Constructing a sidewalk along 9th Street. The project includes curbs, ramps, and drainage improvements.
Start Date: March 30, 2026
End Date: July 31, 2026

******************************************************************

Texas Township

Road: Blue Jay Drive - 10th Street to Bob White Avenue
Current Status: Week of 7/6 lowering manholes and drainage improvements.
Detour: None
Project Information: Milling and paving.
Start Date: June 30, 2026
End Date:July 31, 2026

 

Road: Bob White Avenue - Morning Dove Lane to Warbler Drive
Current Status: Week of 7/6 lowering manholes and drainage improvements.
Detour: None
Project Information: Milling and paving.
Start Date: June 30, 2026
End Date:July 31, 2026

 

Road: Canary Lane - Swallow Avenue to Blue Jay Drive
Current Status: Week of 7/6 lowering manholes and drainage improvements.
Detour: None
Project Information: Milling and paving.
Start Date: June 30, 2026
End Date:July 31, 2026

 

Road: Morning Dove Lane - Swallow Avenue to Blue Jay Drive
Current Status: Week of 7/6 lowering manholes and drainage improvements.
Detour: None
Project Information: Milling and paving.
Start Date: June 30, 2026
End Date:July 31, 2026

 

Road: Blue Spruce Lane - 345' West of Old Stone Circle to 515' South of Green Pine Lane
Current Status: Week of 7/6 lowering manholes and drainage improvements.
Detour: None
Project Information: Milling and paving.
Start Date: June 30, 2026
End Date:July 31, 2026

 

Road: Finch Drive - Blue Spruce Lane to Bob White Avenue
Current Status: Week of 7/6 lowering manholes and drainage improvements.
Detour: None
Project Information: Milling and paving.
Start Date: June 30, 2026
End Date:July 31, 2026

 

Road: Old Oak Circle - Blue Spruce Lane to 250' North of Blue Spruce Lane
Current Status: Week of 7/6 lowering manholes and drainage improvements.
Detour: None
Project Information: Milling and paving.
Start Date: June 30, 2026
End Date:July 31, 2026

 

Road: Old Stone Circle - Blue Spruce Lane to 221' North of Blue Spruce Lane
Current Status: Week of 7/6 lowering manholes and drainage improvements.
Detour: None
Project Information: Milling and paving.
Start Date: June 30, 2026
End Date:July 31, 2026

 

Road: Warbler Drive - Swallow Avenue to Whippoorwill Drive
Current Status: Week of 7/6 lowering manholes and drainage improvements.
Detour: None
Project Information: Milling and paving.
Start Date: June 30, 2026
End Date:July 31, 2026

 

Road: 5th Street - N Eagle Lake Drive to OP Avenue
Current Status: Drainage improvements forthcoming.
Detour: None
Project Information: Tree clearing, milling, and paving.
Start Date: April 6, 2026
End Date: October 15, 2026

 

Road: E Eagle Lake Drive - 950' south of OP Avenue to OP Avenue
Current Status: Drainage improvements forthcoming.
Detour: None
Project Information: Tree clearing, milling, and paving.
Start Date: April 6, 2026
End Date: October 15, 2026

 

Road: 9th Street / O Avenue - 390' west of 9th Street to Cracker Barrel Drive
Current Status: Awaiting fog seal construction joint.
Detour: None
Project Information: Paving
Start Date: April 23, 2026
End Date: October 15, 2026

******************************************************************

Wakeshma Township

Road: X Avenue - 40th Street to 42nd Street
Current Status: Drainage improvements forthcoming week of 7/6.
Detour: None
Project Information: Gravel placement and pulverization.
Start Date: April 13, 2026
End Date: November 15, 2026

******************************************************************

Countywide Projects

Road: Crack filling on various roads in Kalamazoo County.
Current Status: Crack fill continuing in various townships.
Detour: None
Project Information: Traffic to be maintained during project. This is a mobile operation, temporary traffic regulators may be necessary and slight delays are possible. 
Start Date: May 4, 2026
End Date: July 1, 2026

 

Road: Pavement Marking on various roads within Kalamazoo County.
Current Status: Pavement marking work will continue throughout the county, including the installation of raodway markings and pavement legends as part of various road improvement projects.
Detour: Expect delays in work zones. Please use caution and do not follow pavement marking vehicles too closely to help prevent wet paint from getting on your vehicle.
Project Information: Pavement Markings
Start Date: June 1, 2026
End Date: October 15, 2026

 

###

For file attachment (PDF), click here