(posted Sep 04, 2026)
FOR IMMEDIATE RELEASE
DATE: Thursday, September 7, 2026
Sign up for RCKC CONNECT to receive message alerts for road construction, road closures/detours, and general public news from the Road Commission of Kalamazoo County website at: www.kalamazoocountyroads.com
Kalamazoo, MI-
In an effort to keep local drivers informed of the latest traffic and road maintenance operations by the Road Commission, we have provided the following update. For further information call 269-381-3171 or visit RCKC website www.kalamazoocountyroads.com.
“This information is made available to assist motorists in planning for construction delays,” Travis Bartholomew, Managing Director of the Road Commission said. “Motorists are reminded to be alert, slow down, stay informed, and be cautious when approaching a work zone. Remember, these projects signify progress in improving our infrastructure!”
Please note: This information is subject to change. Projects, road closures and timing can change from day to day, depending upon a number of factors, and traffic delays can develop in a matter of minutes due to weather conditions, emergency situations, etc.
******************************************************************
Alamo Township
Road: C Avenue - 6th Street to Ravine Road
Current Status: Ditching and culverts to begin 9/8.
Detour: None
Project Information: RCKC preventive maintenance.
Start Date: April 15, 2026
End Date: October 15, 2026
******************************************************************
Brady Township
Road: West Indian Lake Drive - 1,500' north of UV Avenue to 2,300' north of UV Avenue
Current Status: Milling and paving forthcoming.
Detour: None
Project Information: Milling and paving.
Start Date: April 15, 2026
End Date: October 15, 2026
******************************************************************
Comstock Township
Road: Comstock Avenue - Sprinkle Road to River Street
Current Status: Week of 9/7, hand patching between curb and existing road. Potentially begin milling toward the end of the week.
Detour: Comstock Avenue will be closed to through traffic and detoured using River Street, I-94 BL, and Sprinkle Road.
Project Information: 0.85 miles of asphalt milling and resurfacing, concrete curb and gutter replacement, and storm sewer replacement.
Start Date: June 1, 2026
End Date: September 20, 2026
******************************************************************
Kalamazoo Township
Road: Westwood Drive Garage - Westwood Drive to 275' south of Westwood Drive
Current Status: Week of 9/7, pipe lining.
Detour: None
Project Information: Drainage Rehab.
Start Date: August 19, 2026
End Date: October 15, 2026
Road: Dwillard Drive - 356' south of Kenilworth Avenue to East Main Street
Current Status: Manhole adjustments, roadside restoration.
Detour: None
Project Information: RCKC Preventive Maintenance.
Start Date: April 15, 2026
End Date: October 15, 2026
Road: Ashley Drive - Kenilworth Avenue to East Main Street
Current Status: Manhole adjustments, roadside restoration.
Detour: None
Project Information: RCKC Preventive Maintenance.
Start Date: April 15, 2026
End Date: October 15, 2026
Road: Arthur Avenue - Charles Avenue to East Main Street
Current Status: Manhole adjustments, roadside restoration.
Detour: None
Project Information: RCKC Preventive Maintenance.
Start Date: April 15, 2026
End Date: October 15, 2026
Road: Clearview Street - Kenilworth Avenue to East Main Street
Current Status: Manhole adjustments, roadside restoration.
Detour: None
Project Information: RCKC Preventive Maintenance.
Start Date: April 15, 2026
End Date: October 15, 2026
******************************************************************
Oshtemo Township
Road: M Avenue - Vankal Street to 4th Street
Current Status: Week of 9/7, tree removal to begin.
Detour: None
Project Information: Drainage improvement, milling, and HMA resurfacing.
Start Date: June 1, 2026
End Date: October 15, 2026
Road: W Michigan Avenue - Venture Park Road to Drake Road
Current Status: Week of 9/7, structure adjustments are anticipated. Milling and paving is anticipated to begin the week of 9/14.
Detour: W Michigan Avenue will be closed and detoured using Drake Road and Stadium drive suring paving operations.
Project Information: 0.8 miles of asphalt milling and resurfacing.
Start Date: September 8, 2026
End Date: October 15, 2026
******************************************************************
Prairie Ronde Township
Road: 10th Street - VW Avenue to U Avenue
Current Status: Beginning ditching and culvert placement the week of 9/8.
Detour: None
Project Information: 4" new gravel, drainage improvements, tree removal.
Start Date: September 1, 2026
End Date: October 15, 2026
******************************************************************
Schoolcraft Township
Road: 22nd Street - 2,640' south of U Avenue to U Avenue
Current Status: Roadside restoration.
Detour: None
Project Information: New HMA surface, cold milling, and drainage improvements.
Start Date: September 1, 2026
End Date: October 15, 2026
Road: Starlet Street - South Hill Avenue to Crimora Street
Current Status: Restoration beginning the week of 9/8.
Detour: None
Project Information: New HMA surface, cold milling, and drainage improvements.
Start Date: September 1, 2026
End Date: October 15, 2026
Road: Jasmine Avenue - Crocus Street to 616' east of Honeysuckle Street; Honeysuckle Street - VW Avenue to Jasmine Avenue
Current Status: Week of 9/8, paving scheduled.
Detour: None
Project Information: New HMA surface, cold milling, and drainage improvements.
Start Date: September 1, 2026
End Date: October 15, 2026
******************************************************************
Wakeshma Township
Road: 44th Street - U Avenue to T Avenue
Current Status: Installing culverts the week of 9/8.
Detour: None
Project Information: RCKC preventive maintenance.
Start Date: August 10, 2026
End Date: October 15, 2026
******************************************************************
Countywide Projects
Road: Crack filling on various roads in Kalamazoo County.
Current Status: Crack fill continuing in various townships.
Detour: None
Project Information: Traffic to be maintained during project. This is a mobile operation, temporary traffic regulators may be necessary and slight delays are possible.
Start Date: May 4, 2026
End Date: November 15, 2026
Road: Pavement Marking on various roads within Kalamazoo County.
Current Status: Pavement marking work will continue throughout the county, including the installation of roadway markings and pavement legends as part of various road improvement projects.
Detour: Expect delays in work zones. Please use caution and do not follow pavement marking vehicles too closely to help prevent wet paint from getting on your vehicle.
Project Information: Pavement Markings
Start Date: June 1, 2026
End Date: October 15, 2026
###